FirstNet Authority's Lack of Contract Oversight for Device Connection Targets Puts the NPSBN at Risk of Impacting First Responders' Use of the Network
Date Issued | June 12, 2024 |
---|---|
Report Number | OIG-24-027-A |
Report Type | Audits / Evaluations |
Description |
Our audit found that FirstNet Authority did not adequately assess contractor performance to ensure AT&T achieved the desired results for device connections targets for each state and territory. |